Renewable sites › Minnygap
Minnygap
Minnygap is an operational 25 MW onshore wind farm in Dumfries and Galloway, generating since 15 March 2017. Planning permission was granted on 20 June 2014, 60 months after submission. Operator of record: Minnygap (formerly RES).
Planning and build timeline
| Application submitted | 29 June 2009 |
| Permission granted | 20 June 2014 60 months after submission |
| Operational | 15 March 2017 33 months after consent |
Screening a site of your own?
Dumfries and Galloway approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Minnygap’s recorded coordinate — swap in your own postcode or coordinates.
Dumfries and Galloway’s record on onshore wind
Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 100 | 3.3 km |
Wind Onshore · Operational | 136 | 3.9 km |
Battery · Under Construction | 49.9 | 10.4 km |
Wind Onshore · Operational | 30 | 11.2 km |
Biomass (dedicated) · Operational | 50.4 | 13.7 km |
How big is Minnygap?
Minnygap has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Minnygap?
REPD records the operator as Minnygap (formerly RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Minnygap approved and built?
The application was submitted on 29 June 2009. Permission was granted on 20 June 2014, 60 months later. The site became operational on 15 March 2017, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4437.