Renewable sites › Lochluichart
Lochluichart
Lochluichart is operational in Scotland with a recorded capacity of 51 MW, and has been generating since 2014-05-14.
Planning and build timeline
| Application submitted | 2005-11-21 |
| Permission granted | 2008-12-22 37 months after submission |
| Operational | 2014-05-14 65 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Corriemoillie Wind Onshore · Operational | 54.4 | 3 km |
Lochluichart (Extension) Wind Onshore · Operational | 18 | 3.2 km |
Achanalt Small Hydro · Operational | 3 | 7.7 km |
How big is Lochluichart?
Lochluichart has a recorded installed capacity of 51 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lochluichart?
REPD records the operator as Eneco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lochluichart approved and built?
The application was submitted on 2005-11-21. Permission was granted on 2008-12-22, 37 months later. The site became operational on 2014-05-14, 65 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4123.
Novarly Parcel · official public data, read properly · parcel.novarly.com