Llanbabo Wind Farm
Llanbabo Wind Farm is an operational 20.4 MW onshore wind farm in Isle of Anglesey, generating since 1 October 1997. Planning permission was granted on 19 December 1996, 28 months after submission. Operator of record: MANWEB Generation Holdings.
Planning and build timeline
| Application submitted | 5 August 1994 |
| Permission granted | 19 December 1996 28 months after submission |
| Operational | 1 October 1997 9 months after consent |
Screening a site of your own?
Isle of Anglesey approves 57% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Llanbabo Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Isle of Anglesey’s record on onshore wind
Isle of Anglesey has decided 7 onshore wind schemes and approved 57%, taking a median of 16.1 months. See every onshore wind scheme decision in Isle of Anglesey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.6 | 6.2 km |
Solar Photovoltaics · Under Construction | 49.9 | 6.5 km |
Wind Onshore · Operational | 5.6 | 8.2 km |
Solar Photovoltaics · Operational | 15 | 14.1 km |
How big is Llanbabo Wind Farm?
Llanbabo Wind Farm has a recorded installed capacity of 20.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Llanbabo Wind Farm?
REPD records the operator as MANWEB Generation Holdings. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Llanbabo Wind Farm approved and built?
The application was submitted on 5 August 1994. Permission was granted on 19 December 1996, 28 months later. The site became operational on 1 October 1997, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2582.