Novarly ParcelRenewable planning

Renewable planning Onshore windIsle of Anglesey

Onshore wind planning in Isle of Anglesey

Isle of Anglesey has decided 7 onshore wind schemes and approved 57% of them, taking a median of 16.1 months to decide. Consented capacity: 41 MW. 1 application still awaiting a decision.

57%
Approved
4 granted · 3 refused
16.1 mo
Median decision
UK 11.5 mo
41 MW
Consented
17 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Isle of Anglesey compares

Against the 75 UK authorities with 5+ onshore wind decisions, Isle of Anglesey sits in the 26th percentile for approval rate (11 points below the England average) and the 33rd percentile for speed.

Decisions by year

35Approved — 1 (2011)111Refused — 2 (2015)215Approved — 1 (2016)116
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (8)

SchemeMWStatusDecided
Townland of Meenakeeran, Tullycar Road - Wind Farm & Battery Storage
Meenakeeran Wind Farm Limited · LA11/2025/0701/F
24Application Submitted2025-09-30
Rhyd-y-Groes Wind Farm - repowering
E.On / Eurus (TPG Wind) · 20C102L/EIA/RE · 18.3 mo to decide
9.9Awaiting Construction2016-10-21
Braint Wind Farm
West Coast Energy · 41C125B/EIA/RE · 23.4 mo to decide
2.6Application Refused2015-07-27
Ysgellog 2 Wind Farm
Airvolution Energy · 38C301A/EIA/RE · 9.7 mo to decide
4.6Application Refused2015-01-13
Ystgellog Farm Wind Farm
Airvolution Energy · 11C557B · 7.9 mo to decide
4.6Operational2011-06-21
Llanbabo Wind Farm
MANWEB Generation Holdings · 28.5 mo to decide
20.4Operational1996-12-19
Prysan Wind Farm
South Western Power / Renewable Energy Systems (RES) / NOVERA · 7.6 mo to decide
9.9Application Refused1996-08-06
Trysglwyn Wind Farm
RWE npower · 16.1 mo to decide
5.6Operational1993-12-10

Does Isle of Anglesey approve onshore wind schemes?

Yes — of the 7 onshore wind schemes Isle of Anglesey has decided, 57% were approved (4 granted, 3 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Isle of Anglesey?

The median time from application to decision is 16.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Isle of Anglesey consented?

41 MW has been consented across 4 approved schemes, with 17 MW refused. A further 1 application awaits a decision.

Other technologies in Isle of Anglesey

Solar in Isle of AngleseyBattery storage in Isle of Anglesey

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.