Renewable planning › Onshore wind › Isle of Anglesey
Onshore wind planning in Isle of Anglesey
Isle of Anglesey has decided 7 onshore wind schemes and approved 57% of them, taking a median of 16.1 months to decide. Consented capacity: 41 MW. 1 application still awaiting a decision.
⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Isle of Anglesey compares
Against the 75 UK authorities with 5+ onshore wind decisions, Isle of Anglesey sits in the 26th percentile for approval rate (11 points below the England average) and the 33rd percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (8)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Townland of Meenakeeran, Tullycar Road - Wind Farm & Battery Storage Meenakeeran Wind Farm Limited · LA11/2025/0701/F | 24 | Application Submitted | 2025-09-30 |
Rhyd-y-Groes Wind Farm - repowering E.On / Eurus (TPG Wind) · 20C102L/EIA/RE · 18.3 mo to decide | 9.9 | Awaiting Construction | 2016-10-21 |
Braint Wind Farm West Coast Energy · 41C125B/EIA/RE · 23.4 mo to decide | 2.6 | Application Refused | 2015-07-27 |
Ysgellog 2 Wind Farm Airvolution Energy · 38C301A/EIA/RE · 9.7 mo to decide | 4.6 | Application Refused | 2015-01-13 |
Ystgellog Farm Wind Farm Airvolution Energy · 11C557B · 7.9 mo to decide | 4.6 | Operational | 2011-06-21 |
Llanbabo Wind Farm MANWEB Generation Holdings · 28.5 mo to decide | 20.4 | Operational | 1996-12-19 |
Prysan Wind Farm South Western Power / Renewable Energy Systems (RES) / NOVERA · 7.6 mo to decide | 9.9 | Application Refused | 1996-08-06 |
Trysglwyn Wind Farm RWE npower · 16.1 mo to decide | 5.6 | Operational | 1993-12-10 |
Does Isle of Anglesey approve onshore wind schemes?
Yes — of the 7 onshore wind schemes Isle of Anglesey has decided, 57% were approved (4 granted, 3 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in Isle of Anglesey?
The median time from application to decision is 16.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Isle of Anglesey consented?
41 MW has been consented across 4 approved schemes, with 17 MW refused. A further 1 application awaits a decision.
Other technologies in Isle of Anglesey
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.