Renewable sites › Ystgellog Farm Wind Farm
Ystgellog Farm Wind Farm
Ystgellog Farm Wind Farm is an operational 4.6 MW onshore wind farm in Isle of Anglesey, generating since 30 April 2013. Planning permission was granted on 21 June 2011, 8 months after submission. Operator of record: Airvolution Energy.
Planning and build timeline
| Application submitted | 24 October 2010 |
| Permission granted | 21 June 2011 8 months after submission |
| Operational | 30 April 2013 22 months after consent |
Screening a site of your own?
Isle of Anglesey approves 57% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ystgellog Farm Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Isle of Anglesey’s record on onshore wind
Isle of Anglesey has decided 7 onshore wind schemes and approved 57%, taking a median of 16.1 months. See every onshore wind scheme decision in Isle of Anglesey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 49.9 | 1.9 km |
Wind Onshore · Operational | 5.6 | 4.2 km |
Wind Onshore · Operational | 20.4 | 6.2 km |
How big is Ystgellog Farm Wind Farm?
Ystgellog Farm Wind Farm has a recorded installed capacity of 4.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ystgellog Farm Wind Farm?
REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ystgellog Farm Wind Farm approved and built?
The application was submitted on 24 October 2010. Permission was granted on 21 June 2011, 8 months later. The site became operational on 30 April 2013, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3856.