Bryn yr Odyn Solar Farm
Bryn yr Odyn Solar Farm is operational in Isle of Anglesey with a recorded capacity of 15 MW, and has been generating since 2015-02-28.
Planning and build timeline
| Application submitted | 2013-09-08 |
| Permission granted | 2013-11-06 2 months after submission |
| Operational | 2015-02-28 16 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bodorgan Solar Farm Solar Photovoltaics · Operational | 12.6 | 6.1 km |
Parciau Farm Solar Park Solar Photovoltaics · Operational | 13.9 | 13.3 km |
Llanbabo Wind Farm Wind Onshore · Operational | 20.4 | 14.1 km |
How big is Bryn yr Odyn Solar Farm?
Bryn yr Odyn Solar Farm has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bryn yr Odyn Solar Farm?
REPD records the operator as New Forest Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bryn yr Odyn Solar Farm approved and built?
The application was submitted on 2013-09-08. Permission was granted on 2013-11-06, 2 months later. The site became operational on 2015-02-28, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2353.