Renewable sites › Little Cheyne Court Wind Farm
Little Cheyne Court Wind Farm
Little Cheyne Court Wind Farm is operational in Folkestone and Hythe with a recorded capacity of 59.8 MW, and has been generating since 2009-06-01.
Planning and build timeline
| Application submitted | 2002-11-28 |
| Permission granted | 2005-10-18 35 months after submission |
| Operational | 2009-06-01 43 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
- SSSI — Dungeness, Romney Marsh and Rye Bay SSSI
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Sycamore Farm Solar Photovoltaics · Operational | 20 | 4.9 km |
Dengemarsh Road Solar Photovoltaics · Operational | 1 | 6.9 km |
Kenardington Place Farm Solar Photovoltaics · Operational | 7 | 10.9 km |
How big is Little Cheyne Court Wind Farm?
Little Cheyne Court Wind Farm has a recorded installed capacity of 59.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Little Cheyne Court Wind Farm?
REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Little Cheyne Court Wind Farm approved and built?
The application was submitted on 2002-11-28. Permission was granted on 2005-10-18, 35 months later. The site became operational on 2009-06-01, 43 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3096.