Dengemarsh Road is an operational 1 MW solar farm in Folkestone and Hythe, generating since 14 December 2016. Planning permission was granted on 13 April 2017, 2 months after submission. Operator of record: Tudor Roof Tile Co.
Planning and build timeline
| Application submitted | 21 February 2017 |
| Permission granted | 13 April 2017 2 months after submission |
| Operational | 14 December 2016 |
Screening a site of your own?
Folkestone and Hythe approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Dengemarsh Road’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Ramsar wetland — Dungeness, Romney Marsh and Rye Bay
- SSSI — Dungeness, Romney Marsh and Rye Bay SSSI
- Special Protection Area — Dungeness, Romney Marsh and Rye Bay
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Folkestone and Hythe’s record on solar
Folkestone and Hythe has decided 8 solar farms and approved 100%, taking a median of 2.5 months. See every solar farm decision in Folkestone and Hythe →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 20 | 6.8 km |
Wind Onshore · Operational | 59.8 | 6.9 km |
How big is Dengemarsh Road?
Dengemarsh Road has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dengemarsh Road?
REPD records the operator as Tudor Roof Tile Co. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dengemarsh Road approved and built?
The application was submitted on 21 February 2017. Permission was granted on 13 April 2017, 2 months later. The site became operational on 14 December 2016.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6376.