Langford Solar Farm is operational in Mid Devon with a recorded capacity of 35 MW, and has been generating since 2025-08-02.
Planning and build timeline
| Application submitted | 2018-11-28 |
| Permission granted | 2022-12-05 48 months after submission |
| Operational | 2025-08-02 32 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Langford Solar Farm Solar Photovoltaics · Operational | 35 | 0 km |
Winham Farm Solar Photovoltaics · Operational | 5 | 1.8 km |
Paytherden Solar Farm (Peradon) Solar Photovoltaics · Under Construction | 49 | 2.9 km |
Kia Ora Farm Solar Photovoltaics · Operational | 1.8 | 4.3 km |
Little Toms - Solar Farm Solar Photovoltaics · Under Construction | 5 | 5.5 km |
Stoneshill Farm Solar Photovoltaics · Operational | 5 | 6.2 km |
SAUNDERCROFT SOLAR FARM Solar Photovoltaics · Operational | 7 | 6.8 km |
Higher Pirzwell Solar Farm Solar Photovoltaics · Operational | 1.2 | 6.9 km |
How big is Langford Solar Farm?
Langford Solar Farm has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Langford Solar Farm?
REPD records the operator as JBM Solar Projects. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Langford Solar Farm approved and built?
The application was submitted on 2018-11-28. Permission was granted on 2022-12-05, 48 months later. The site became operational on 2025-08-02, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 19164.