Renewable sites › Land at High Point Farm
Land at High Point Farm
Land at High Point Farm is an operational 4.5 MW solar farm in Shropshire, generating since 31 March 2017. Planning permission was granted on 16 March 2016, 17 months after submission. Operator of record: TGC Renewables.
Planning and build timeline
| Application submitted | 22 October 2014 |
| Permission granted | 16 March 2016 17 months after submission |
| Operational | 31 March 2017 12 months after consent |
Screening a site of your own?
Shropshire approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land at High Point Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Shropshire’s record on solar
Shropshire has decided 68 solar farms and approved 94%, taking a median of 3.2 months. See every solar farm decision in Shropshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 0.3 | 7.4 km |
Solar Photovoltaics · Operational | 5 | 13.3 km |
How big is Land at High Point Farm?
Land at High Point Farm has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at High Point Farm?
REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at High Point Farm approved and built?
The application was submitted on 22 October 2014. Permission was granted on 16 March 2016, 17 months later. The site became operational on 31 March 2017, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4701.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode