Land at Green Farm
Land at Green Farm is an operational 1 MW solar farm in Herefordshire, County of, generating since 21 June 2016. Planning permission was granted on 30 September 2015, 2 months after submission. Operator of record: Private Developer.
Planning and build timeline
| Application submitted | 29 July 2015 |
| Permission granted | 30 September 2015 2 months after submission |
| Operational | 21 June 2016 9 months after consent |
Screening a site of your own?
Herefordshire, County of approves 80% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land at Green Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Herefordshire, County of’s record on solar
Herefordshire, County of has decided 25 solar farms and approved 80%, taking a median of 3 months. See every solar farm decision in Herefordshire, County of →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 8.2 km |
Solar Photovoltaics · Operational | 45 | 10.6 km |
Battery · Operational | — | 10.6 km |
Battery · Operational | 20 | 10.9 km |
Solar Photovoltaics · Operational | 45 | 11.1 km |
How big is Land at Green Farm?
Land at Green Farm has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Green Farm?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Green Farm approved and built?
The application was submitted on 29 July 2015. Permission was granted on 30 September 2015, 2 months later. The site became operational on 21 June 2016, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5545.