Lancaster Wastewater Treatment Works is an operational 1.2 MW solar farm in Lancaster, generating since 7 April 2016. Planning permission was granted on 20 January 2017, 5 months after submission. Operator of record: United Utilities.

1.2 MW
Capacity
as recorded in REPD
Operational
Status
since 7 April 2016
Solar Photovoltaics
Technology
United Utilities
Lancaster
Authority
England

Planning and build timeline

Application submitted12 August 2016
Permission granted20 January 2017
5 months after submission
Operational7 April 2016

Screening a site of your own?

RedlineUK · £39

Lancaster approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lancaster Wastewater Treatment Works’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Lancaster’s record on solar

Lancaster has decided 13 solar farms and approved 100%, taking a median of 4.1 months. See every solar farm decision in Lancaster

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
6.20.4 km
Solar Photovoltaics · Under Construction
16.51.6 km
Wind Onshore · Operational
22.9 km
Wind Onshore · Operational
7.53.5 km
Landfill Gas · Operational
24 km
Landfill Gas · Operational
44 km
Wind Onshore · Operational
1.54.1 km
Solar Photovoltaics · Operational
55.3 km

How big is Lancaster Wastewater Treatment Works?

Lancaster Wastewater Treatment Works has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lancaster Wastewater Treatment Works?

REPD records the operator as United Utilities. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lancaster Wastewater Treatment Works approved and built?

The application was submitted on 12 August 2016. Permission was granted on 20 January 2017, 5 months later. The site became operational on 7 April 2016.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6189.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode