Fanny House Farm/Heysham Moss

Fanny House Farm/Heysham Moss is an operational 1.5 MW onshore wind farm in Lancaster, generating since 1 February 2015. Planning permission was granted on 16 October 2012, 21 months after submission. Operator of record: Blue Energy.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2015
Wind Onshore
Technology
Blue Energy
Lancaster
Authority
England

Planning and build timeline

Application submitted27 January 2011
Permission granted16 October 2012
21 months after submission
Operational1 February 2015
28 months after consent

Screening a site of your own?

RedlineUK · £39

Lancaster approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Fanny House Farm/Heysham Moss’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Lancaster’s record on onshore wind

Lancaster has decided 5 onshore wind schemes and approved 80%, taking a median of 9.9 months. See every onshore wind scheme decision in Lancaster

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
7.50.6 km
Solar Photovoltaics · Operational
51.6 km
Landfill Gas · Operational
23.2 km
Landfill Gas · Operational
43.2 km
Solar Photovoltaics · Operational
6.23.7 km
Solar Photovoltaics · Operational
1.24.1 km
Solar Photovoltaics · Under Construction
16.55.1 km
Wind Onshore · Operational
27 km

How big is Fanny House Farm/Heysham Moss?

Fanny House Farm/Heysham Moss has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fanny House Farm/Heysham Moss?

REPD records the operator as Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fanny House Farm/Heysham Moss approved and built?

The application was submitted on 27 January 2011. Permission was granted on 16 October 2012, 21 months later. The site became operational on 1 February 2015, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3792.