Renewable sites › Kilbraur Windfarm Farlary - Extension
Kilbraur Windfarm Farlary - Extension
Kilbraur Windfarm Farlary - Extension is an operational 20 MW onshore wind farm in Scotland, generating since 1 September 2011. Planning permission was granted on 1 December 2009, 9 months after submission. Operator of record: Falck Renewables.
Planning and build timeline
| Application submitted | 13 March 2009 |
| Permission granted | 1 December 2009 9 months after submission |
| Operational | 1 September 2011 21 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Kilbraur Windfarm Farlary - Extension’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 47.5 | 7.1 km |
Wind Onshore · Operational | 70 | 7.6 km |
Wind Onshore · Operational | 47 | 10.7 km |
How big is Kilbraur Windfarm Farlary - Extension?
Kilbraur Windfarm Farlary - Extension has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kilbraur Windfarm Farlary - Extension?
REPD records the operator as Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kilbraur Windfarm Farlary - Extension approved and built?
The application was submitted on 13 March 2009. Permission was granted on 1 December 2009, 9 months later. The site became operational on 1 September 2011, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2673.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode