Renewable sitesGordonbush

Gordonbush

Gordonbush is operational in Scottish Government (S36) with a recorded capacity of 70 MW, and has been generating since 2012-06-12.

70 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-06-12
Wind Onshore
Technology
Scottish and Southern Energy (SSE)
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2003-06-17
Permission granted2008-04-09
58 months after submission
Operational2012-06-12
50 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Gordonbush (extension)
Wind Onshore · Operational
473.2 km
Kilbraur Windfarm
Wind Onshore · Operational
47.56.3 km
Kilbraur Windfarm Farlary - Extension
Wind Onshore · Operational
207.6 km

How big is Gordonbush?

Gordonbush has a recorded installed capacity of 70 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gordonbush?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gordonbush approved and built?

The application was submitted on 2003-06-17. Permission was granted on 2008-04-09, 58 months later. The site became operational on 2012-06-12, 50 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3662.