Hatherden Farm

Hatherden Farm is an operational 49.9 MW solar farm in Test Valley. Planning permission was granted on 5 June 2020, 6 months after submission. Operator of record: Nextpower SPV 10 Limited.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
no operational date
Solar Photovoltaics
Technology
Nextpower SPV 10 Limited
Test Valley
Authority
England

Planning and build timeline

Application submitted20 December 2019
Permission granted5 June 2020
6 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Test Valley approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hatherden Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Test Valley’s record on solar

Test Valley has decided 37 solar farms and approved 95%, taking a median of 5 months. See every solar farm decision in Test Valley

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
54.5 km
Solar Photovoltaics · Operational
406.8 km
Solar Photovoltaics · Operational
59 km
Solar Photovoltaics · Operational
79.4 km
Solar Photovoltaics · Operational
79.6 km
Solar Photovoltaics · Operational
59.9 km
Solar Photovoltaics · Operational
4.210.9 km
Solar Photovoltaics · Operational
511.9 km

How big is Hatherden Farm?

Hatherden Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hatherden Farm?

REPD records the operator as Nextpower SPV 10 Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hatherden Farm approved and built?

The application was submitted on 20 December 2019. Permission was granted on 5 June 2020, 6 months later. REPD does not record an operational date.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7425.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode