Renewable sites › Gunnista, Bressay Solar panels
Gunnista, Bressay Solar panels
Gunnista, Bressay Solar panels is operational in Shetland Islands, and has been generating since 2021-09-11.
Planning and build timeline
| Application submitted | 2021-02-11 |
| Permission granted | 2021-07-09 5 months after submission |
| Operational | 2021-09-11 2 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Northern Isles New Energy Solution (NINES) 1 Battery · Operational | 1 | 3.4 km |
Gremista Wind Farm Wind Onshore · Operational | 3 | 5.5 km |
Burradale Hill Wind Onshore · Operational | 3.7 | 7 km |
How big is Gunnista, Bressay Solar panels?
REPD does not record an installed capacity for Gunnista, Bressay Solar panels.
Who operates Gunnista, Bressay Solar panels?
REPD records the operator as Bressay Development Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gunnista, Bressay Solar panels approved and built?
The application was submitted on 2021-02-11. Permission was granted on 2021-07-09, 5 months later. The site became operational on 2021-09-11, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8451.
Novarly Parcel · official public data, read properly · parcel.novarly.com