Gunfleet Sands II� is an operational 64.8 MW offshore wind farm in DECC (S36), generating since 24 July 2009. Planning permission was granted on 28 February 2008, 8 months after submission. Operator of record: Orsted (formerly Dong Energy).
Planning and build timeline
| Application submitted | 18 June 2007 |
| Permission granted | 28 February 2008 8 months after submission |
| Operational | 24 July 2009 17 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Gunfleet Sands II�’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
- Special Protection Area — Outer Thames Estuary
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Offshore · Operational | 108 | 2 km |
Wind Offshore · Operational | 12 | 4.6 km |
Solar Photovoltaics · Operational | 0.9 | 11.6 km |
Wind Onshore · Operational | 10.3 | 13 km |
How big is Gunfleet Sands II�?
Gunfleet Sands II� has a recorded installed capacity of 64.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gunfleet Sands II�?
REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gunfleet Sands II� approved and built?
The application was submitted on 18 June 2007. Permission was granted on 28 February 2008, 8 months later. The site became operational on 24 July 2009, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2489.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode