Ewe Hill

Ewe Hill is an operational 13.8 MW onshore wind farm in Scotland, generating since 30 May 2016. Planning permission was granted on 7 June 2010, 74 months after submission. Operator of record: Scottish Power Renewables.

13.8 MW
Capacity
as recorded in REPD
Operational
Status
since 30 May 2016
Wind Onshore
Technology
Scottish Power Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted7 April 2004
Permission granted7 June 2010
74 months after submission
Operational30 May 2016
72 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ewe Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
36.80 km
Wind Onshore · Operational
36.82.1 km
Biomass (dedicated) · Operational
50.45.9 km
Anaerobic Digestion · Operational
1.212.8 km
Wind Onshore · Operational
4812.8 km
Wind Onshore · Operational
3014.5 km

How big is Ewe Hill?

Ewe Hill has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ewe Hill?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ewe Hill approved and built?

The application was submitted on 7 April 2004. Permission was granted on 7 June 2010, 74 months later. The site became operational on 30 May 2016, 72 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4015.