Renewable sites › Crossdykes
Crossdykes
Crossdykes is an operational 48 MW onshore wind farm in Dumfries and Galloway, generating since 1 June 2021. Planning permission was granted on 27 June 2019, 8 months after submission. Operator of record: Muirhall Energy.
Planning and build timeline
| Application submitted | 8 November 2018 |
| Permission granted | 27 June 2019 8 months after submission |
| Operational | 1 June 2021 23 months after consent |
Screening a site of your own?
Dumfries and Galloway approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Crossdykes’s recorded coordinate — swap in your own postcode or coordinates.
Dumfries and Galloway’s record on onshore wind
Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 10 | 6.8 km |
Wind Onshore · Operational | 30 | 9.4 km |
Wind Onshore · Operational | 36.8 | 12.8 km |
Wind Onshore · Operational | 13.8 | 12.8 km |
Wind Onshore · Operational | 36.8 | 13 km |
Biomass (dedicated) · Operational | 50.4 | 13.5 km |
How big is Crossdykes?
Crossdykes has a recorded installed capacity of 48 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Crossdykes?
REPD records the operator as Muirhall Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Crossdykes approved and built?
The application was submitted on 8 November 2018. Permission was granted on 27 June 2019, 8 months later. The site became operational on 1 June 2021, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4633.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode