Novarly ParcelRenewable sites

Renewable sitesCrossdykes

Crossdykes

Crossdykes is operational in Dumfries and Galloway with a recorded capacity of 48 MW, and has been generating since 2021-06-01.

48 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-06-01
Wind Onshore
Technology
Muirhall Energy
Dumfries and Galloway
Authority
Scotland

Planning and build timeline

Application submitted2018-11-08
Permission granted2019-06-27
8 months after submission
Operational2021-06-01
23 months after consent

Dumfries and Galloway’s record on onshore wind

Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway

Other built sites within 15 km

SiteMWDistance
Craig Wind Farm
Wind Onshore · Operational
106.8 km
Solwaybank Wind Farm
Wind Onshore · Operational
309.4 km
Ewe Hill (extension)
Wind Onshore · Operational
36.812.8 km
Ewe Hill
Wind Onshore · Operational
13.812.8 km
Minsca
Wind Onshore · Operational
36.813 km
Stevens Croft
Biomass (dedicated) · Operational
50.413.5 km

How big is Crossdykes?

Crossdykes has a recorded installed capacity of 48 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crossdykes?

REPD records the operator as Muirhall Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crossdykes approved and built?

The application was submitted on 2018-11-08. Permission was granted on 2019-06-27, 8 months later. The site became operational on 2021-06-01, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4633.

Novarly Parcel · official public data, read properly · parcel.novarly.com