Renewable sitesDunkeswell Airfield

Dunkeswell Airfield

Dunkeswell Airfield is an operational 2 MW solar farm in East Devon, generating since 11 March 2015. Planning permission was granted on 11 March 2014, 6 months after submission. Operator of record: Lumicity.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 11 March 2015
Solar Photovoltaics
Technology
Lumicity
East Devon
Authority
England

Planning and build timeline

Application submitted30 August 2013
Permission granted11 March 2014
6 months after submission
Operational11 March 2015
12 months after consent

Screening a site of your own?

RedlineUK · £39

East Devon approves 87% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dunkeswell Airfield’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.26.3 km
Solar Photovoltaics · Operational
4.89.3 km
Solar Photovoltaics · Operational
7.59.8 km
Solar Photovoltaics · Operational
2.110.1 km
Solar Photovoltaics · Under Construction
4910.4 km
Solar Photovoltaics · Operational
1.211 km
Solar Photovoltaics · Operational
511.2 km
Solar Photovoltaics · Operational
3511.2 km

How big is Dunkeswell Airfield?

Dunkeswell Airfield has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dunkeswell Airfield?

REPD records the operator as Lumicity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dunkeswell Airfield approved and built?

The application was submitted on 30 August 2013. Permission was granted on 11 March 2014, 6 months later. The site became operational on 11 March 2015, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1454.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode