Novarly ParcelRenewable sites

Renewable sitesDesford Brick Works, Bagworth - Solar Panels

Desford Brick Works, Bagworth - Solar Panels

Desford Brick Works, Bagworth - Solar Panels is an operational 2.6 MW solar farm in Hinckley and Bosworth, generating since 1 April 2024. Planning permission was granted on 14 July 2022, 2 months after submission. Operator of record: Leicestershire County Council.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2024
Solar Photovoltaics
Technology
Leicestershire County Council
Hinckley and Bosworth
Authority
England

Planning and build timeline

Application submitted27 May 2022
Permission granted14 July 2022
2 months after submission
Operational1 April 2024
21 months after consent

Screening a site of your own?

RedlineUK · £39

Hinckley and Bosworth approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Desford Brick Works, Bagworth - Solar Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Hinckley and Bosworth’s record on solar

Hinckley and Bosworth has decided 25 solar farms and approved 96%, taking a median of 3 months. See every solar farm decision in Hinckley and Bosworth

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
51.5 km
Wind Onshore · Operational
1.61.8 km
Solar Photovoltaics · Operational
2.73.2 km
Solar Photovoltaics · Operational
53.3 km
Solar Photovoltaics · Operational
53.5 km
Solar Photovoltaics · Operational
63.6 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Operational
4.95 km

How big is Desford Brick Works, Bagworth - Solar Panels?

Desford Brick Works, Bagworth - Solar Panels has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Desford Brick Works, Bagworth - Solar Panels?

REPD records the operator as Leicestershire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Desford Brick Works, Bagworth - Solar Panels approved and built?

The application was submitted on 27 May 2022. Permission was granted on 14 July 2022, 2 months later. The site became operational on 1 April 2024, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11513.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode