Renewable sites › Craig Wind Farm
Craig Wind Farm
Craig Wind Farm is operational in Dumfries and Galloway with a recorded capacity of 10 MW, and has been generating since 2007-10-01.
Planning and build timeline
| Application submitted | 2003-07-23 |
| Permission granted | 2004-11-09 16 months after submission |
| Operational | 2007-10-01 35 months after consent |
Dumfries and Galloway’s record on onshore wind
Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crossdykes Wind Onshore · Operational | 48 | 6.8 km |
Solwaybank Wind Farm Wind Onshore · Operational | 30 | 7.5 km |
How big is Craig Wind Farm?
Craig Wind Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Craig Wind Farm?
REPD records the operator as Craig Wind Farm Co. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Craig Wind Farm approved and built?
The application was submitted on 2003-07-23. Permission was granted on 2004-11-09, 16 months later. The site became operational on 2007-10-01, 35 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4524.
Novarly Parcel · official public data, read properly · parcel.novarly.com