Novarly ParcelRenewable sites

Renewable sitesCregganconroe

Cregganconroe

Cregganconroe is operational in Fermanagh and Omagh with a recorded capacity of 13.8 MW, and has been generating since 2017-01-04.

13.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-01-04
Wind Onshore
Technology
Gaelectric Developments/ CGN Europe Energy
Fermanagh and Omagh
Authority
Northern Ireland

Planning and build timeline

Application submitted2006-09-29
Permission granted2010-09-08
47 months after submission
Operational2017-01-04
76 months after consent

Fermanagh and Omagh’s record on onshore wind

Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh

Other built sites within 15 km

SiteMWDistance
Crockbrack
Wind Onshore · Operational
21.8 km
Inishative
Wind Onshore · Operational
13.86.5 km
Crockdun
Wind Onshore · Operational
12.57.5 km
Crockagarron Ext
Wind Onshore · Operational
2.58.1 km
Eshmore
Wind Onshore · Operational
6.98.4 km
Crockagarran
Wind Onshore · Operational
158.4 km
Crockbaravally Wind Farm
Wind Onshore · Operational
7.58.9 km
Gortfinbar
Wind Onshore · Operational
159.1 km

How big is Cregganconroe?

Cregganconroe has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cregganconroe?

REPD records the operator as Gaelectric Developments/ CGN Europe Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cregganconroe approved and built?

The application was submitted on 2006-09-29. Permission was granted on 2010-09-08, 47 months later. The site became operational on 2017-01-04, 76 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4653.