Renewable sites › Cour Wind Farm
Cour Wind Farm
Cour Wind Farm is an operational 20.5 MW onshore wind farm in Argyll and Bute, generating since 1 December 2016. Planning permission was granted on 17 October 2012, 29 months after submission. Operator of record: Octopus Investments/Blue Energy.
Planning and build timeline
| Application submitted | 21 May 2010 |
| Permission granted | 17 October 2012 29 months after submission |
| Operational | 1 December 2016 49 months after consent |
Screening a site of your own?
Argyll and Bute approves 58% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Cour Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Argyll and Bute’s record on onshore wind
Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 15.8 | 6.8 km |
Wind Onshore · Operational | 22.5 | 10.8 km |
Wind Onshore · Operational | 15 | 12.4 km |
Wind Onshore · Operational | 29.7 | 13.6 km |
Wind Onshore · Operational | 43.7 | 13.6 km |
How big is Cour Wind Farm?
Cour Wind Farm has a recorded installed capacity of 20.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cour Wind Farm?
REPD records the operator as Octopus Investments/Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cour Wind Farm approved and built?
The application was submitted on 21 May 2010. Permission was granted on 17 October 2012, 29 months later. The site became operational on 1 December 2016, 49 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3772.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode