Novarly ParcelRenewable sites

Renewable sitesCarland Cross Wind Farm - Storage

Carland Cross Wind Farm - Storage

Carland Cross Wind Farm - Storage is a 1 MW battery storage site under construction in Cornwall. REPD does not record the planning grant date. Operator of record: Scottish Power.

1 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Scottish Power
Cornwall
Authority
England

Planning and build timeline

Application submitted12 August 2018
Permission grantednot recorded
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Cornwall approves 96% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Carland Cross Wind Farm - Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on battery storage

Cornwall has decided 25 battery storage schemes and approved 96%, taking a median of 3.4 months. See every battery storage scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
200.4 km
Solar Photovoltaics · Under Construction
102.7 km
Wind Onshore · Operational
2.33.8 km
Solar Photovoltaics · Operational
65.3 km
Solar Photovoltaics · Operational
1.75.3 km
Wind Onshore · Operational
15.4 km
Solar Photovoltaics · Operational
1.25.4 km
Solar Photovoltaics · Operational
55.9 km

How big is Carland Cross Wind Farm - Storage?

Carland Cross Wind Farm - Storage has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Carland Cross Wind Farm - Storage?

REPD records the operator as Scottish Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Carland Cross Wind Farm - Storage approved and built?

The application was submitted on 12 August 2018. REPD does not record a grant date. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7034.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode