Bonerbo Wind Turbines

Bonerbo Wind Turbines is an operational 1.5 MW onshore wind farm in Fife, generating since 15 December 2014. Planning permission was granted on 14 May 2013, 10 months after submission. Operator of record: Messrs Stevenson, Watson and Brunton.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 December 2014
Wind Onshore
Technology
Messrs Stevenson, Watson and Brunton
Fife
Authority
Scotland

Planning and build timeline

Application submitted10 July 2012
Permission granted14 May 2013
10 months after submission
Operational15 December 2014
19 months after consent

Screening a site of your own?

RedlineUK · £39

Fife approves 54% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bonerbo Wind Turbines’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fife’s record on onshore wind

Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
6.514.7 km
Solar Photovoltaics · Operational
114.8 km

How big is Bonerbo Wind Turbines?

Bonerbo Wind Turbines has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bonerbo Wind Turbines?

REPD records the operator as Messrs Stevenson, Watson and Brunton. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bonerbo Wind Turbines approved and built?

The application was submitted on 10 July 2012. Permission was granted on 14 May 2013, 10 months later. The site became operational on 15 December 2014, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3370.