Bruar Hydro Scheme

Bruar Hydro Scheme is operational in Perth and Kinross with a recorded capacity of 1.9 MW, and has been generating since 2015-12-20.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-20
Small Hydro
Technology
Bruar Hydro / Gilkes
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted2012-02-10
Permission granted2012-08-16
6 months after submission
Operational2015-12-20
40 months after consent

Other built sites within 15 km

SiteMWDistance
Blair Castle Caravan Park, Blair Atholl - Solar Farm
Solar Photovoltaics · Operational
0.168.8 km

How big is Bruar Hydro Scheme?

Bruar Hydro Scheme has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bruar Hydro Scheme?

REPD records the operator as Bruar Hydro / Gilkes. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bruar Hydro Scheme approved and built?

The application was submitted on 2012-02-10. Permission was granted on 2012-08-16, 6 months later. The site became operational on 2015-12-20, 40 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 478.