Betton Abbots is operational in Shropshire with a recorded capacity of 1.3 MW, and has been generating since 2003-08-01.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2003-08-01
Landfill Gas
Technology
SITA UK / Natural Power
Shropshire
Authority
England

Planning and build timeline

Application submitted2000-03-13
Permission granted2000-05-17
2 months after submission
Operational2003-08-01
38 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Condover (Green Farm)
Solar Photovoltaics · Operational
10.21.6 km
Condover Airfield
Solar Photovoltaics · Operational
12.34.2 km
Pitchford
Solar Photovoltaics · Operational
10.25.4 km
Sundorne Grove
Solar Photovoltaics · Operational
207.2 km
Battlefield EfW
EfW Incineration · Operational
88.1 km
Tiddiecross Solar Farm
Solar Photovoltaics · Operational
10.510.5 km
Rushmoor Lane Farm (Cheshire Coppice)
Solar Photovoltaics · Operational
513 km
Steeraway Farm - Solar Farm
Solar Photovoltaics · Under Construction
3014.2 km

How big is Betton Abbots?

Betton Abbots has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Betton Abbots?

REPD records the operator as SITA UK / Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Betton Abbots approved and built?

The application was submitted on 2000-03-13. Permission was granted on 2000-05-17, 2 months later. The site became operational on 2003-08-01, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 701.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council