Woolley Hill Wind Farm is operational in Huntingdonshire with a recorded capacity of 10 MW, and has been generating since 2014-04-30.
Planning and build timeline
| Application submitted | 2010-11-11 |
| Permission granted | 2012-03-23 16 months after submission |
| Operational | 2014-04-30 25 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Huntingdonshire’s record on onshore wind
Huntingdonshire has decided 10 onshore wind schemes and approved 80%, taking a median of 13.9 months. See every onshore wind scheme decision in Huntingdonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
ROOKERY FARM SOLAR FARM Solar Photovoltaics · Operational | 5.3 | 5.7 km |
Station Farm Landfill Scheme Landfill Gas · Operational | 2 | 6.6 km |
Littleyhey Prison Solar Farm Solar Photovoltaics · Operational | 0.5 | 6.6 km |
Common Barn Wind Farm Wind Onshore · Operational | 6.2 | 7.1 km |
Abbots Ripton Solar Farm (ext.) Solar Photovoltaics · Operational | 3.9 | 8.6 km |
Abbots Ripton Solar Farm Solar Photovoltaics · Operational | 24.7 | 8.6 km |
Abbey Farm Solar Photovoltaics · Operational | 9 | 10.1 km |
Godmanchester Landfill Gas · Operational | 3 | 10.5 km |
How big is Woolley Hill Wind Farm?
Woolley Hill Wind Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Woolley Hill Wind Farm?
REPD records the operator as Aviva. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Woolley Hill Wind Farm approved and built?
The application was submitted on 2010-11-11. Permission was granted on 2012-03-23, 16 months later. The site became operational on 2014-04-30, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4175.
Novarly Parcel · official public data, read properly · parcel.novarly.com