Renewable sitesWick Farm Solar Park

Wick Farm Solar Park

Wick Farm Solar Park is an operational 14.6 MW solar farm in Somerset, generating since 1 July 2016. Planning permission was granted on 28 October 2014, 2 months after submission. Operator of record: Hadstone Energy/ Communities for Renewables.

14.6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2016
Solar Photovoltaics
Technology
Hadstone Energy/ Communities for Renewables
Somerset
Authority
England

Planning and build timeline

Application submitted20 August 2014
Permission granted28 October 2014
2 months after submission
Operational1 July 2016
20 months after consent

Screening a site of your own?

RedlineUK · £39

Somerset approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wick Farm Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
2.82.3 km
Solar Photovoltaics · Operational
6.86.4 km
Solar Photovoltaics · Operational
10.27.3 km
Solar Photovoltaics · Operational
38.8 km
Solar Photovoltaics · Operational
7.210.1 km
Solar Photovoltaics · Operational
5.510.4 km
Solar Photovoltaics · Operational
8.310.6 km
Solar Photovoltaics · Under Construction
19.811.2 km

How big is Wick Farm Solar Park?

Wick Farm Solar Park has a recorded installed capacity of 14.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wick Farm Solar Park?

REPD records the operator as Hadstone Energy/ Communities for Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wick Farm Solar Park approved and built?

The application was submitted on 20 August 2014. Permission was granted on 28 October 2014, 2 months later. The site became operational on 1 July 2016, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2274.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode