Novarly ParcelRenewable sites

Renewable sitesStroupster Wind Farm - additional turbine

Stroupster Wind Farm - additional turbine

Stroupster Wind Farm - additional turbine is operational in Highland with a recorded capacity of 2.3 MW, and has been generating since 2015-10-15.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-10-15
Wind Onshore
Technology
Greencoat UK Wind/Bay Wa .r.e/ SunGift
Highland
Authority
Scotland

Planning and build timeline

Application submitted2013-11-05
Permission granted2014-01-20
2 months after submission
Operational2015-10-15
21 months after consent

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Hill of Stroupster Windfarm
Wind Onshore · Operational
29.90.9 km
Lochend Wind Farm
Wind Onshore · Operational
9.27.8 km
Causeymire
Wind Onshore · Operational
48.314.6 km

How big is Stroupster Wind Farm - additional turbine?

Stroupster Wind Farm - additional turbine has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stroupster Wind Farm - additional turbine?

REPD records the operator as Greencoat UK Wind/Bay Wa .r.e/ SunGift. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stroupster Wind Farm - additional turbine approved and built?

The application was submitted on 2013-11-05. Permission was granted on 2014-01-20, 2 months later. The site became operational on 2015-10-15, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3433.