Stroupster Wind Farm - additional turbine is an operational 2.3 MW onshore wind farm in Highland, generating since 15 October 2015. Planning permission was granted on 20 January 2014, 2 months after submission. Operator of record: Greencoat UK Wind/Bay Wa .r.e/ SunGift.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 15 October 2015
Wind Onshore
Technology
Greencoat UK Wind/Bay Wa .r.e/ SunGift
Highland
Authority
Scotland

Planning and build timeline

Application submitted5 November 2013
Permission granted20 January 2014
2 months after submission
Operational15 October 2015
21 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Stroupster Wind Farm - additional turbine’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
29.90.9 km
Wind Onshore · Operational
9.27.8 km
Wind Onshore · Operational
48.314.6 km

How big is Stroupster Wind Farm - additional turbine?

Stroupster Wind Farm - additional turbine has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stroupster Wind Farm - additional turbine?

REPD records the operator as Greencoat UK Wind/Bay Wa .r.e/ SunGift. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stroupster Wind Farm - additional turbine approved and built?

The application was submitted on 5 November 2013. Permission was granted on 20 January 2014, 2 months later. The site became operational on 15 October 2015, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3433.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode