Hill of Stroupster Windfarm

Hill of Stroupster Windfarm is an operational 29.9 MW onshore wind farm in Highland, generating since 3 December 2015. Planning permission was granted on 8 April 2010, 58 months after submission. Operator of record: Greencoat UK Wind.

29.9 MW
Capacity
as recorded in REPD
Operational
Status
since 3 December 2015
Wind Onshore
Technology
Greencoat UK Wind
Highland
Authority
Scotland

Planning and build timeline

Application submitted7 June 2005
Permission granted8 April 2010
58 months after submission
Operational3 December 2015
68 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hill of Stroupster Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.30.9 km
Wind Onshore · Operational
9.27.8 km

How big is Hill of Stroupster Windfarm?

Hill of Stroupster Windfarm has a recorded installed capacity of 29.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hill of Stroupster Windfarm?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hill of Stroupster Windfarm approved and built?

The application was submitted on 7 June 2005. Permission was granted on 8 April 2010, 58 months later. The site became operational on 3 December 2015, 68 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4121.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode