Renewable sitesStrathy North

Strathy North

Strathy North is operational in Scottish Government (S36) with a recorded capacity of 67.7 MW, and has been generating since 2015-12-01.

67.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-01
Wind Onshore
Technology
Scottish and Southern Energy (SSE)
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2007-01-12
Permission granted2011-11-22
58 months after submission
Operational2015-12-01
48 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Strathy Wood
Wind Onshore · Under Construction
62.42 km
Strathy South
Wind Onshore · Under Construction
2086 km
Phase 1 Bettyhill Wind Farm
Wind Onshore · Operational
510.7 km

How big is Strathy North?

Strathy North has a recorded installed capacity of 67.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Strathy North?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Strathy North approved and built?

The application was submitted on 2007-01-12. Permission was granted on 2011-11-22, 58 months later. The site became operational on 2015-12-01, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4625.