Renewable sites › Strathy North
Strathy North
Strathy North is an operational 67.7 MW onshore wind farm in Scotland, generating since 1 December 2015. Planning permission was granted on 22 November 2011, 58 months after submission. Operator of record: Scottish and Southern Energy (SSE).
Planning and build timeline
| Application submitted | 12 January 2007 |
| Permission granted | 22 November 2011 58 months after submission |
| Operational | 1 December 2015 48 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Strathy North’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Under Construction | 62.4 | 2 km |
Wind Onshore · Under Construction | 208 | 6 km |
Wind Onshore · Operational | 5 | 10.7 km |
How big is Strathy North?
Strathy North has a recorded installed capacity of 67.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Strathy North?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Strathy North approved and built?
The application was submitted on 12 January 2007. Permission was granted on 22 November 2011, 58 months later. The site became operational on 1 December 2015, 48 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4625.