Phase 1 Bettyhill Wind Farm

Phase 1 Bettyhill Wind Farm is an operational 5 MW onshore wind farm in Highland, generating since 4 June 2013. Planning permission was granted on 31 August 2011, 46 months after submission. Operator of record: North British Windpower Ltd.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 4 June 2013
Wind Onshore
Technology
North British Windpower Ltd
Highland
Authority
Scotland

Planning and build timeline

Application submitted9 November 2007
Permission granted31 August 2011
46 months after submission
Operational4 June 2013
21 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Phase 1 Bettyhill Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
67.710.7 km
Wind Onshore · Under Construction
62.412.2 km
Wind Onshore · Under Construction
20812.8 km

How big is Phase 1 Bettyhill Wind Farm?

Phase 1 Bettyhill Wind Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Phase 1 Bettyhill Wind Farm?

REPD records the operator as North British Windpower Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Phase 1 Bettyhill Wind Farm approved and built?

The application was submitted on 9 November 2007. Permission was granted on 31 August 2011, 46 months later. The site became operational on 4 June 2013, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3380.