Renewable sites › Phase 1 Bettyhill Wind Farm
Phase 1 Bettyhill Wind Farm
Phase 1 Bettyhill Wind Farm is an operational 5 MW onshore wind farm in Highland, generating since 4 June 2013. Planning permission was granted on 31 August 2011, 46 months after submission. Operator of record: North British Windpower Ltd.
Planning and build timeline
| Application submitted | 9 November 2007 |
| Permission granted | 31 August 2011 46 months after submission |
| Operational | 4 June 2013 21 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Phase 1 Bettyhill Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 67.7 | 10.7 km |
Wind Onshore · Under Construction | 62.4 | 12.2 km |
Wind Onshore · Under Construction | 208 | 12.8 km |
How big is Phase 1 Bettyhill Wind Farm?
Phase 1 Bettyhill Wind Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Phase 1 Bettyhill Wind Farm?
REPD records the operator as North British Windpower Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Phase 1 Bettyhill Wind Farm approved and built?
The application was submitted on 9 November 2007. Permission was granted on 31 August 2011, 46 months later. The site became operational on 4 June 2013, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3380.