Renewable sites › St Francis Farm
St Francis Farm
St Francis Farm is an operational 4 MW solar farm in Rother, generating since 19 March 2015. Planning permission was granted on 26 August 2014, 6 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 28 February 2014 |
| Permission granted | 26 August 2014 6 months after submission |
| Operational | 19 March 2015 7 months after consent |
Screening a site of your own?
Rother approves 82% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with St Francis Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Rother’s record on solar
Rother has decided 11 solar farms and approved 82%, taking a median of 2.5 months. See every solar farm decision in Rother →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | — | 0.8 km |
Solar Photovoltaics · Operational | 11.5 | 1.8 km |
Landfill Gas · Operational | 3 | 5.3 km |
Landfill Gas · Operational | 1 | 5.3 km |
Wind Onshore · Operational | 7.5 | 13.8 km |
Solar Photovoltaics · Operational | 0.2 | 14.5 km |
How big is St Francis Farm?
St Francis Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates St Francis Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was St Francis Farm approved and built?
The application was submitted on 28 February 2014. Permission was granted on 26 August 2014, 6 months later. The site became operational on 19 March 2015, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1324.