Renewable sites › Pebsham (Extension)
Pebsham (Extension)
Pebsham (Extension) is an operational 1 MW landfill gas site in Hastings, generating since 1 November 2004. Planning permission was granted on 14 October 2004, 2 months after submission. Operator of record: Biffa.
Planning and build timeline
| Application submitted | 11 August 2004 |
| Permission granted | 14 October 2004 2 months after submission |
| Operational | 1 November 2004 1 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Hastings: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pebsham (Extension)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 3 | 0 km |
Solar Photovoltaics · Operational | 4 | 5.3 km |
Battery · Under Construction | — | 5.5 km |
Solar Photovoltaics · Operational | 11.5 | 6.9 km |
How big is Pebsham (Extension)?
Pebsham (Extension) has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pebsham (Extension)?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pebsham (Extension) approved and built?
The application was submitted on 11 August 2004. Permission was granted on 14 October 2004, 2 months later. The site became operational on 1 November 2004, 1 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 782.