South Shore Holiday Village is an operational 0.4 MW solar farm in East Riding of Yorkshire, generating since 18 May 2021. Planning permission was granted on 14 December 2020, 18 months after submission. Operator of record: East Riding of Yorkshire Council.
Planning and build timeline
| Application submitted | 25 June 2019 |
| Permission granted | 14 December 2020 18 months after submission |
| Operational | 18 May 2021 5 months after consent |
Screening a site of your own?
East Riding of Yorkshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with South Shore Holiday Village’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on solar
East Riding of Yorkshire has decided 57 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 29.7 | 1.8 km |
Wind Onshore · Operational | 30 | 7.7 km |
How big is South Shore Holiday Village?
South Shore Holiday Village has a recorded installed capacity of 0.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates South Shore Holiday Village?
REPD records the operator as East Riding of Yorkshire Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was South Shore Holiday Village approved and built?
The application was submitted on 25 June 2019. Permission was granted on 14 December 2020, 18 months later. The site became operational on 18 May 2021, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7559.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode