Snettisham Solar Farm is operational in North Norfolk with a recorded capacity of 2.7 MW, and has been generating since 2017-03-28.

2.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-28
Solar Photovoltaics
Technology
Solar Associates
North Norfolk
Authority
England

Planning and build timeline

Application submitted2014-10-20
Permission granted2016-03-24
17 months after submission
Operational2017-03-28
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Norfolk’s record on solar

North Norfolk has decided 26 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in North Norfolk

Other built sites within 15 km

SiteMWDistance
North Creake Airfield
Solar Photovoltaics · Operational
207.4 km
South Creake Solar Farm
Solar Photovoltaics · Operational
2610.1 km
Stody Estate Solar Array
Solar Photovoltaics · Operational
0.4910.5 km
West Raynham
Solar Photovoltaics · Operational
49.914.6 km

How big is Snettisham Solar Farm?

Snettisham Solar Farm has a recorded installed capacity of 2.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Snettisham Solar Farm?

REPD records the operator as Solar Associates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Snettisham Solar Farm approved and built?

The application was submitted on 2014-10-20. Permission was granted on 2016-03-24, 17 months later. The site became operational on 2017-03-28, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4739.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council