Novarly ParcelRenewable sites

Renewable sitesNorth Creake Airfield

North Creake Airfield

North Creake Airfield is an operational 20 MW solar farm in North Norfolk, generating since 27 March 2014. Planning permission was granted on 21 March 2013, 1 months after submission. Operator of record: British Solar Renewables (formerly known as Solar Power Generation).

20 MW
Capacity
as recorded in REPD
Operational
Status
since 27 March 2014
Solar Photovoltaics
Technology
British Solar Renewables (formerly known as Solar Power Generation)
North Norfolk
Authority
England

Planning and build timeline

Application submitted11 February 2013
Permission granted21 March 2013
1 months after submission
Operational27 March 2014
12 months after consent

Screening a site of your own?

RedlineUK · £39

North Norfolk approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with North Creake Airfield’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Norfolk’s record on solar

North Norfolk has decided 26 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in North Norfolk

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
266.3 km
Solar Photovoltaics · Operational
2.77.4 km
Wind Onshore · Operational
13.89.9 km
Wind Onshore · Operational
8.210.8 km
Solar Photovoltaics · Operational
49.914.1 km

How big is North Creake Airfield?

North Creake Airfield has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates North Creake Airfield?

REPD records the operator as British Solar Renewables (formerly known as Solar Power Generation). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was North Creake Airfield approved and built?

The application was submitted on 11 February 2013. Permission was granted on 21 March 2013, 1 months later. The site became operational on 27 March 2014, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2046.