Renewable sites › North Creake Airfield
North Creake Airfield
North Creake Airfield is operational in North Norfolk with a recorded capacity of 20 MW, and has been generating since 2014-03-27.
Planning and build timeline
| Application submitted | 2013-02-11 |
| Permission granted | 2013-03-21 1 months after submission |
| Operational | 2014-03-27 12 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Norfolk’s record on solar
North Norfolk has decided 26 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in North Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
South Creake Solar Farm Solar Photovoltaics · Operational | 26 | 6.3 km |
Snettisham Solar Farm Solar Photovoltaics · Operational | 2.7 | 7.4 km |
Jack's Lane Wind Farm Wind Onshore · Operational | 13.8 | 9.9 km |
Chiplow Wind Onshore · Operational | 8.2 | 10.8 km |
West Raynham Solar Photovoltaics · Operational | 49.9 | 14.1 km |
How big is North Creake Airfield?
North Creake Airfield has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates North Creake Airfield?
REPD records the operator as British Solar Renewables (formerly known as Solar Power Generation). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was North Creake Airfield approved and built?
The application was submitted on 2013-02-11. Permission was granted on 2013-03-21, 1 months later. The site became operational on 2014-03-27, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2046.
Novarly Parcel · official public data, read properly · parcel.novarly.com