Stody Estate Solar Array
Stody Estate Solar Array is an operational 0.49 MW solar farm in North Norfolk, generating since 6 October 2021. Planning permission was granted on 22 October 2021, 11 months after submission. Operator of record: Stody Estate Limited.
Planning and build timeline
| Application submitted | 6 November 2020 |
| Permission granted | 22 October 2021 11 months after submission |
| Operational | 6 October 2021 |
Screening a site of your own?
North Norfolk approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Stody Estate Solar Array’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Norfolk’s record on solar
North Norfolk has decided 26 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in North Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 3.6 | 7.7 km |
Solar Photovoltaics · Operational | 10.2 | 9.5 km |
Solar Photovoltaics · Operational | 5 | 10.1 km |
Solar Photovoltaics · Operational | 2.7 | 10.5 km |
How big is Stody Estate Solar Array?
Stody Estate Solar Array has a recorded installed capacity of 0.49 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Stody Estate Solar Array?
REPD records the operator as Stody Estate Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Stody Estate Solar Array approved and built?
The application was submitted on 6 November 2020. Permission was granted on 22 October 2021, 11 months later. The site became operational on 6 October 2021.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8203.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode