Novarly ParcelRenewable sites

Renewable sitesSnetterton Biomass Plant

Snetterton Biomass Plant

Snetterton Biomass Plant is an operational 44.2 MW biomass plant in Breckland, generating since 13 December 2016. Planning permission was granted on 18 July 2012, 6 months after submission. Operator of record: Burmeister & Wain Scandinavian Contractor A/S (BWSC).

44.2 MW
Capacity
as recorded in REPD
Operational
Status
since 13 December 2016
Biomass (dedicated)
Technology
Burmeister & Wain Scandinavian Contractor A/S (BWSC)
Breckland
Authority
England

Planning and build timeline

Application submitted19 January 2012
Permission granted18 July 2012
6 months after submission
Operational13 December 2016
53 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Breckland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Snetterton Biomass Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.6 km
Solar Photovoltaics · Under Construction
305.4 km
Anaerobic Digestion · Operational
15.4 km
Solar Photovoltaics · Operational
85.7 km
Solar Photovoltaics · Operational
59.8 km
Solar Photovoltaics · Operational
0.3410.4 km
Solar Photovoltaics · Operational
0.213.2 km
Solar Photovoltaics · Operational
5.214.7 km

How big is Snetterton Biomass Plant?

Snetterton Biomass Plant has a recorded installed capacity of 44.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Snetterton Biomass Plant?

REPD records the operator as Burmeister & Wain Scandinavian Contractor A/S (BWSC). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Snetterton Biomass Plant approved and built?

The application was submitted on 19 January 2012. Permission was granted on 18 July 2012, 6 months later. The site became operational on 13 December 2016, 53 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 185.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode