Renewable sites › Sibelco Brassington
Sibelco Brassington
Sibelco Brassington is an operational 2.3 MW onshore wind farm in Derbyshire Dales, generating since 15 September 2016. Planning permission was granted on 21 March 2012, 11 months after submission. Operator of record: Sibelco/ Golconda.
Planning and build timeline
| Application submitted | 11 April 2011 |
| Permission granted | 21 March 2012 11 months after submission |
| Operational | 15 September 2016 54 months after consent |
Screening a site of your own?
Derbyshire Dales approves 60% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Sibelco Brassington’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Derbyshire Dales’s record on onshore wind
Derbyshire Dales has decided 5 onshore wind schemes and approved 60%, taking a median of 11.3 months. See every onshore wind scheme decision in Derbyshire Dales →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5 | 0.5 km |
Wind Onshore · Operational | 8 | 0.8 km |
Solar Photovoltaics · Operational | 4.7 | 7.4 km |
Solar Photovoltaics · Operational | 5 | 8.9 km |
Solar Photovoltaics · Operational | 3 | 10 km |
How big is Sibelco Brassington?
Sibelco Brassington has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Sibelco Brassington?
REPD records the operator as Sibelco/ Golconda. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Sibelco Brassington approved and built?
The application was submitted on 11 April 2011. Permission was granted on 21 March 2012, 11 months later. The site became operational on 15 September 2016, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3382.