Land at Dayfields Farm

Land at Dayfields Farm is operational in Derbyshire Dales with a recorded capacity of 4.7 MW, and has been generating since 2016-12-30.

4.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-30
Solar Photovoltaics
Technology
TGC Renewables
Derbyshire Dales
Authority
England

Planning and build timeline

Application submitted2015-03-03
Permission granted2016-03-09
12 months after submission
Operational2016-12-30
10 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Derbyshire Dales’s record on solar

Derbyshire Dales has decided 13 solar farms and approved 92%, taking a median of 2.9 months. See every solar farm decision in Derbyshire Dales

Other built sites within 15 km

SiteMWDistance
Lady Hole Farm
Solar Photovoltaics · Operational
33 km
Smith Hall Farm Solar Park
Solar Photovoltaics · Operational
54 km
Carsington Pasture
Wind Onshore · Operational
86.6 km
Sibelco Brassington
Wind Onshore · Operational
2.37.4 km
Ryder Point Quarry Wind Turbines
Wind Onshore · Operational
57.6 km

How big is Land at Dayfields Farm?

Land at Dayfields Farm has a recorded installed capacity of 4.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Dayfields Farm?

REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Dayfields Farm approved and built?

The application was submitted on 2015-03-03. Permission was granted on 2016-03-09, 12 months later. The site became operational on 2016-12-30, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5063.