Novarly ParcelRenewable sites

Renewable sitesRUDGE FARM SOLAR FARM

RUDGE FARM SOLAR FARM

RUDGE FARM SOLAR FARM is an operational 7 MW solar farm in Wiltshire, generating since 28 March 2013. Planning permission was granted on 21 December 2012, 5 months after submission. Operator of record: Orta Solar.

7 MW
Capacity
as recorded in REPD
Operational
Status
since 28 March 2013
Solar Photovoltaics
Technology
Orta Solar
Wiltshire
Authority
England

Planning and build timeline

Application submitted26 July 2012
Permission granted21 December 2012
5 months after submission
Operational28 March 2013
3 months after consent

Screening a site of your own?

RedlineUK · £39

Wiltshire approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with RUDGE FARM SOLAR FARM’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
177.3 km

How big is RUDGE FARM SOLAR FARM?

RUDGE FARM SOLAR FARM has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates RUDGE FARM SOLAR FARM?

REPD records the operator as Orta Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was RUDGE FARM SOLAR FARM approved and built?

The application was submitted on 26 July 2012. Permission was granted on 21 December 2012, 5 months later. The site became operational on 28 March 2013, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1091.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode