Novarly ParcelRenewable sites

Renewable sitesRavens Close

Ravens Close

Ravens Close is operational in North Yorkshire with a recorded capacity of 5 MW, and has been generating since 2017-03-14.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-14
Solar Photovoltaics
Technology
NESF (formerly Tau Solar)
North Yorkshire
Authority
England

Planning and build timeline

Application submitted2015-02-02
Permission granted2016-03-21
14 months after submission
Operational2017-03-14
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on solar

North Yorkshire has decided 105 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Caton Moor Windfarm Repowering
Wind Onshore · Operational
169.5 km

How big is Ravens Close?

Ravens Close has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ravens Close?

REPD records the operator as NESF (formerly Tau Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ravens Close approved and built?

The application was submitted on 2015-02-02. Permission was granted on 2016-03-21, 14 months later. The site became operational on 2017-03-14, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5017.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council