Renewable sitesRavens Close

Ravens Close

Ravens Close is an operational 5 MW solar farm in North Yorkshire, generating since 14 March 2017. Planning permission was granted on 21 March 2016, 14 months after submission. Operator of record: NESF (formerly Tau Solar).

5 MW
Capacity
as recorded in REPD
Operational
Status
since 14 March 2017
Solar Photovoltaics
Technology
NESF (formerly Tau Solar)
North Yorkshire
Authority
England

Planning and build timeline

Application submitted2 February 2015
Permission granted21 March 2016
14 months after submission
Operational14 March 2017
12 months after consent

Screening a site of your own?

RedlineUK · £39

North Yorkshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ravens Close’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on solar

North Yorkshire has decided 105 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
169.5 km

How big is Ravens Close?

Ravens Close has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ravens Close?

REPD records the operator as NESF (formerly Tau Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ravens Close approved and built?

The application was submitted on 2 February 2015. Permission was granted on 21 March 2016, 14 months later. The site became operational on 14 March 2017, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5017.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode