Penare Farm Solar Farm

Penare Farm Solar Farm is an operational 11 MW solar farm in Cornwall, generating since 18 March 2014. Planning permission was granted on 26 April 2013, 4 months after submission. Operator of record: British Solar Renewables (formerly Solar Power Generation).

11 MW
Capacity
as recorded in REPD
Operational
Status
since 18 March 2014
Solar Photovoltaics
Technology
British Solar Renewables (formerly Solar Power Generation)
Cornwall
Authority
England

Planning and build timeline

Application submitted27 December 2012
Permission granted26 April 2013
4 months after submission
Operational18 March 2014
11 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Penare Farm Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
2.90.4 km
Solar Photovoltaics · Operational
7.71.4 km
Wind Onshore · Operational
2.32.4 km
Solar Photovoltaics · Operational
73.6 km
Solar Photovoltaics · Operational
53.8 km
Solar Photovoltaics · Operational
64.3 km
Solar Photovoltaics · Operational
1.54.5 km
Solar Photovoltaics · Operational
7.24.7 km

How big is Penare Farm Solar Farm?

Penare Farm Solar Farm has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Penare Farm Solar Farm?

REPD records the operator as British Solar Renewables (formerly Solar Power Generation). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Penare Farm Solar Farm approved and built?

The application was submitted on 27 December 2012. Permission was granted on 26 April 2013, 4 months later. The site became operational on 18 March 2014, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2008.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode