Novarly ParcelRenewable sites

Renewable sitesChiplow

Chiplow

Chiplow is operational in King's Lynn and West Norfolk with a recorded capacity of 8.2 MW, and has been generating since 2016-04-30.

8.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-04-30
Wind Onshore
Technology
Blue Energy
King's Lynn and West Norfolk
Authority
England

Planning and build timeline

Application submitted2010-05-26
Permission granted2012-05-24
24 months after submission
Operational2016-04-30
47 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

King's Lynn and West Norfolk’s record on onshore wind

King's Lynn and West Norfolk has decided 5 onshore wind schemes and approved 80%, taking a median of 21.2 months. See every onshore wind scheme decision in King's Lynn and West Norfolk

Other built sites within 15 km

SiteMWDistance
Jack's Lane Wind Farm
Wind Onshore · Operational
13.83 km
South Creake Solar Farm
Solar Photovoltaics · Operational
265.5 km
West Raynham
Solar Photovoltaics · Operational
49.98.2 km
North Creake Airfield
Solar Photovoltaics · Operational
2010.8 km
Claypit Moor Solar Farm (Lexham)
Solar Photovoltaics · Operational
7.913.7 km

How big is Chiplow?

Chiplow has a recorded installed capacity of 8.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chiplow?

REPD records the operator as Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chiplow approved and built?

The application was submitted on 2010-05-26. Permission was granted on 2012-05-24, 24 months later. The site became operational on 2016-04-30, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4657.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council