New Rendy Farm
New Rendy Farm is an operational 4.8 MW solar farm in Somerset, generating since 15 December 2013. Planning permission was granted on 29 May 2013, 3 months after submission. Operator of record: TGC Renewables.
Planning and build timeline
| Application submitted | 5 March 2013 |
| Permission granted | 29 May 2013 3 months after submission |
| Operational | 15 December 2013 7 months after consent |
Screening a site of your own?
Somerset approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with New Rendy Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Nutrient-neutrality catchment — Tone Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 4.9 | 1.5 km |
Landfill Gas · Operational | 2.4 | 2.3 km |
Battery · Operational | 30 | 3.5 km |
Solar Photovoltaics · Operational | 5 | 3.7 km |
Solar Photovoltaics · Under Construction | 0.17 | 4 km |
Solar Photovoltaics · Operational | 5 | 4.5 km |
Solar Photovoltaics · Operational | 8.2 | 5 km |
Solar Photovoltaics · Operational | 2 | 5.9 km |
How big is New Rendy Farm?
New Rendy Farm has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates New Rendy Farm?
REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was New Rendy Farm approved and built?
The application was submitted on 5 March 2013. Permission was granted on 29 May 2013, 3 months later. The site became operational on 15 December 2013, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1750.