Renewable sitesLimes Farm Solar Farm

Limes Farm Solar Farm

Limes Farm Solar Farm is an operational 4.6 MW solar farm in South Kesteven, generating since 28 March 2013. Planning permission was granted on 27 April 2011, 2 months after submission. Operator of record: Lark Energy.

4.6 MW
Capacity
as recorded in REPD
Operational
Status
since 28 March 2013
Solar Photovoltaics
Technology
Lark Energy
South Kesteven
Authority
England

Planning and build timeline

Application submitted25 February 2011
Permission granted27 April 2011
2 months after submission
Operational28 March 2013
23 months after consent

Screening a site of your own?

RedlineUK · £39

South Kesteven approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Limes Farm Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Kesteven’s record on solar

South Kesteven has decided 28 solar farms and approved 86%, taking a median of 3.1 months. See every solar farm decision in South Kesteven

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
16.47.8 km
Biomass (dedicated) · Operational
14.511.8 km
Anaerobic Digestion · Operational
1.815 km

How big is Limes Farm Solar Farm?

Limes Farm Solar Farm has a recorded installed capacity of 4.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Limes Farm Solar Farm?

REPD records the operator as Lark Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Limes Farm Solar Farm approved and built?

The application was submitted on 25 February 2011. Permission was granted on 27 April 2011, 2 months later. The site became operational on 28 March 2013, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1555.